Copyright © 2011-13 Helical Pile World, LLC.  All Rights Reserved.

Home | Engineers | Manufacturers | Installation Contractors | News | Technical Advisors | Contact Us

Links | Advertise | Terms of Use | Privacy Policy

Helical Pile World eNews Subscription Home Helical Pile World - The Global Information Source For The Helical Pier Industry

Soil Nails and Shotcrete Facing Used to Stop Sloughing on a 1:1 Slope Caused by Excessive Rainfall


December, 2006

T-OZ Construction Co.

Lake Bay, WA

253-884-1114

www.tozcon.com

Project Name & Location:
Aljoya House at Mercer Island, Mercer Island, WA
Project Date:
December, 2006
Project Type:
Helical Anchors as Soil Nails to Anchor a Shotcrete Retaining Wall
Helical Pile Installation Contractor:

General Contractor:
Geotechnical Engineers:
T-OZ Construction Co. - Lakebay, WA

WG Clark Construction Co. - Mercer Island, WA

Associated Earth Sciences, Inc. - Kirkland, WA
Helical Anchor  Specifications:
(14)  1.5” dia, SS5 Chance Anchors, with 8”, 10”, 12” Helicies; 20 KIPS Allowable Tension Load, Galvanized
Soils & Embedment Depth:
Lawton silt at point of entry, moist to very moist, slightly fractured to non-fractured, with increased plasticity with increasing depth 14 blowcount to 24 blowcount at anticipated anchor TIP elev; 30 ft embedment depth
Project Timeline:
3 Days
Helical Pile Manufacturer:
AB Chance - Centralia, MO

Project Overview

Continuous very heavy rains caused sloughing of the soils above an existing soldier pile wall.  A 1:1 cut had been created from the adjacent property line to the solider pile wall, and the slope was failing.  There was significant concern about the impact on the adjacent office building if the sloughing was allowed to continue unchecked. The forecast for continued rainfall led to the urgency for the construction of a soil nail and shotcrete facing to stabilize the slope.  Helical screw anchors were chosen for this project because of the ability to install them with small, hand-portable equipment, the lack of spoils, the immediate verifiability of the anchor capacities and the ability to immediately apply shotcrete after anchor installation.

Two crews were mobilized to work off man-lifts to install the anchors to depths ranging from 32 to 38 lineal feet with torques up to 4,600 ft. Lbs. The anchors were installed in two rows, 7 to a row with one verification load test performed on an anchor in each row.  Although the sloughing had created a bench to work from at some of the anchor locations along the top row, the sloughing created a dangerous slope along the lower row thus requiring crews on the slope to be roped and tethered at all times to anchors installed in the foundation of the adjacent building.

Specialists in Foundation Piering

and Underpinning Systems